Water systems testing schedule: backflow, TMVs, hot water, cooling towers, grease traps

The water systems in a building answer to more authorities than any other discipline: the water utility, the plumbing code, a public health regulation and, for a commercial kitchen, a trade waste agreement. This guide sets out the routine tests and services each one requires, how often, who attends, and what has to be lodged or kept. Standards are referenced by designation; the standard itself holds the detail.

How to read this page

Intervals marked as a regulation, standard or authority requirement are drawn from the NSW Public Health Regulation 2022 as explained by NSW Health, water authority trade waste and backflow policies, and AS/NZS 2845.3, AS 4032.3, AS/NZS 3500.4 and AS/NZS 3666 as summarised by the regulators and the industry. Where an interval is common practice rather than a requirement, it is marked as recommended practice. Section and clause numbers are quoted only where the source states them.

AS/NZS 3500 is the plumbing and drainage installation standard behind the Plumbing Code of Australia; like the electrical Wiring Rules it says how to build a system, and only its operation and maintenance appendix speaks to what happens afterwards. The recurring duties come from elsewhere: the water authority requires testable backflow devices to be registered and tested annually; AS 4032.3 sets the field-test interval for thermostatic mixing valves; the trade waste agreement sets the grease trap interval; and in New South Wales the Public Health Regulation 2022 sets a monthly test, a five-yearly plan and an annual audit for every cooling tower. The other states run equivalent frameworks with their own forms and authorities.

Who does what

Owner and staff tasks are the temperature checks, the visual walks and the paperwork: lodging certificates, keeping the register, watching the reportable thresholds. Everything that involves a test instrument or opening a device is licensed work: backflow testing needs an accredited tester, TMV testing needs a plumber with the TMV endorsement, cooling tower sampling goes to a NATA-accredited laboratory and the risk plan and audit need a competent person who is independent of the occupier for the audit. The owner or facilities manager stays responsible for the schedule and the records whoever attends.

Routine tests and services, by system

Backflow prevention devices

Thermostatic mixing valves (TMVs)

TMVs are required at every accessible outlet in facilities for young children, older people and people with a disability under the plumbing code and state regulations; a valve that has drifted is a scalding risk and a liability, which is why the test record matters.

Hot water systems

Cooling towers (NSW Public Health Regulation 2022)

Cooling towers are the one water asset where the interval is written into public health law rather than a standard. Warm water systems in hospitals, aged care, hairdressing and childcare premises are notified to council under the same Regulation and operated to AS/NZS 3666.2. Other states run equivalent schemes; check the health department of the state the building is in.

Grease traps

Rainwater and non-potable supplies

Where a rainwater tank tops up from mains, the backflow device on the top-up line joins the annual test above, the cross-connection to drinking water is checked annually, screens and first-flush diverters are cleaned quarterly, and the tank is desludged every three to five years, under the rainwater provisions of AS/NZS 3500.1. Non-potable pipework carries the lilac marking and signage the standard requires.

What the owner has to lodge and keep

The annual backflow test certificate, lodged with the water authority and kept. The TMV test and service record for each valve, with the outlet temperature readings. The hot water service record and relief valve replacements. For a cooling tower: the council register entry and unique identification number, the monthly laboratory results, any reportable-result notification, the risk management plan and its certificate, and the annual audit certificate, all kept on site and available to the council. For a grease trap: every cleaning certificate and the trade waste reports.

Turning the schedule into a register

The intervals above only hold when every backflow device, TMV, hot water unit, cooling tower and grease trap in the building is listed with its interval, its contractor and where the certificate lives. That is an asset register with a maintenance planner on top of it. Standara's library carries these assets with the tasks and intervals attached, so selecting what the building has produces the 12-month schedule, and the compliance report is the record the water authority, the council or the insurer asks for. How to build a facilities asset register covers the site walk; the AS 1851 maintenance schedule and the electrical testing schedule cover the fire and electrical systems that sit beside these on the same statement.

Related

See the water schedule in the demo See pricing

You now have the test rhythm for every water system in the building, the authority behind each interval, and the certificates that prove it.